Friday 7 December 2007

Stonework finished - last windows in

Its taken a bit longer but all in good time, the stonework has been completed at the garage, front door and around the sunroom.
Garage

Sunroom


Front Door.


Last windows in now aswell. Sunroom, front door and front window and the stain glass window (designed by myself.)

Designed window.


So finally the house is sealed up, next tasks were to get the scaffolding down. done by Dec 1st. New year tasks now to get the digger in for all the drains and heating pipes to garage, get a condensed oil boiler and the key ingredient - ELECTRICITY, sorted, so we can warm up the house and get going on the next steps.

Electrician back first, then plumber, tiler to be sorted. might try some painting over the xmas holidays. furniture buying.

INTERIORS progress.
Stairs - awaiting final drawings and prices. Kitchen booked for end Jan - start Feb. My bed bought ( 1st one a bit too long so new one sorted now). Dining table and chairs ordered. Tiles picked for downstairs(hall, sunroom, kitchen and utility). Over xmas wooden floors for sitting and tv rooms to be sorted, with the stairs carpet, and onto landing. Plenty of furniture spotted, so awaiting the lotto numbers to be able to pay for it all :o)))