Monday, 15 October 2007

up to Oct 15th

Finally 2 buckets of colour render arrived on on 10th October so plasterer could do the back wall of house, then up on the scaffolding again to paint the sills.

Inside the electricians got all 1st fix done by Friday evening.

Insulating guys came on Sat morning, did about a 1/4 of the attic with kingspan, and didn't come back til today Monday. pressure on them now as the slabbing team arrived to meet the delivery of plasterboards so they are going to start on ground floor today and once insulation in roof and between joists they'll start upstairs.

Stonemason due on later this week, so steel order in for over the windows/doors of sunroom and front door and garage.

busy week, no new pictures.