Tuesday, 5 June 2007

Ground floor External Walls up

Didn't get a photo of the finished floor, and now another week has passed and there are external walls up. ICF structure walls, for outside and inside central loadbearing wall.


Sunroom not done yet, blocks laid incorrectly to hold in the concrete being poured. Door from kitchen to sunroom wasn't cut out so that is to be cut now... special blades required for that. Not too bad a job given that i was off taking it easy in the Canaries for the week.
Next job is to get the concrete slab company in to measure up and they take 2weeks to deliver. meanwhile, garage walls are to commence this week and also internal block walls to be put in place.