Monday, 30 July 2007

Roof on 30 July - 3 Aug

As the concrete dried in the walls, the carpenters were busy cutting the rafters for the sunroom roof and got started straight away.
Monday 30th July - internal block walls being built up today and tomorrow so then the carpenters will be up working on the main roof.
Talk of chimney pots and plastering chimney in the next few weeks to get the roof finished off. very fast and exciting.
Just keeping a few steps ahead of the guys with the next tradesmen is proving okay... (so far).

Its Thursday - all window sills in.
Going to cast the sills around the stonework areas - over front door and sunroom. Chimneys are built up and i managed to get Black Chimney Pots rather than the terracotta coloured ones.
Carpenters working at serious pace. All stud walls upstairs are in, had some minor adjustments but they're working out well.
Attic space is nearly laid out.. and roof beams are going into place.

Plasterer organised to plaster the chimney stacks by early next week so the lads can finish off roofing by end of next week.
Scaffolding up at front and back. Sides to be done as Plasterer and fascias and soffits and gutters are going up.

Stain glass windows designed so hopefully they company will be able to make them up.

Photo of roof progress on Thurs Aug 2nd.

So in summary as we hit the Bank Holiday weekend in August.....
Its now 15 weeks since the ditch was opened and the photos above are evidence of the progress made. With the weathermen declaring this suumer one of the wettest summers in a long time, anytime i've needed a dry spell to keep going, Sammy Sunshine has done his best. I've been lucky.. and long may this luck continue.

Next weeks update -> Roof on, first sign of colour on the chimneys, line up the stonemason to start and hopefully i'll have checked out a garage front door.

Thursday, 19 July 2007

Upstairs walls built over 1 week.

Took a while to get pre-cast measured up and ordered and approved but just 5 days later it arrived on site. Got soapblocks up to mark out rooms, plumber and vacuum system in to lay out pipes. All the while the garage got a roof on. Sat 14th July concrete came to screed off the pre-cast floor. Now waiting the guys to come back for ICF walls on exterior for upstairs. Sunroom also being done this time round.
23rd July -> Amvic ICF guys back onsite and started work on the upstairs walls.

Monday Morning Photo

Monday evening photo



Tuesday evening Photo



Wednesday Photo

Skipped thursday as i forgot the camera.. but the gables were finished and the sunroom started.

Friday - The big pour
All done on time, concrete arrived around 10am, and poured into the walls. 13 cars onsite as the team run round to make sure all goes well. click on photo to see larger view.



Windows are measured up, and currently designing stained glass for front door and window by stairs.
Gutters measured up for on garage and to be ordered.

Still a bit slow on the stonemason and plasterer but i'll get there. Prices coming in now so hopefully they'll be able to line up with the current schedule of work.

Carpenter hoping to have house roofed for August Bank holiday w/end before his holidays so i am thrilled with this deadline (that i didn't have to set).

Tuesday, 26 June 2007

New Photos

Finally got a sunny day to try take some photos of the latest activities on site. This is a view from inside the gate.




Window sills are on the way. Garage really taking shape. Acquired a free window from the folks for the garage so i'm saving a bit of dosh!! Window to be placed on near wall of photo.


Security on site so far has not been an issue but with the birth of new calf, i think i'll have the place supervised for free over the next few months ->







Interesting times with the measuring up of the pre-cast floor, head height on the stairs etc. Engineer and company working to find the right solution -> getting a "cantilevered slab" to allow for a steep rise on first part of stairs and then extend the landing back towards the gable for the last 3 steps after the half landing! Photo to follow once pre-cast appears on site.

My reclaimed Limestone (from Dromineer) has arrived from Nenagh, first load is the loose stone for the front gate entrance, that stone will stay put for a while.
Bagged stone to come over w/end for the sunroom, front door and front of garage.

Thursday, 21 June 2007

The Waiting game

Well the guys have finally returned to take the 2nd measuring with the internal block wall for the pre-cast slab so now its sit and wait time.. Ha ha yeah right.
Do you know what size openings for the chimneys, stairs, do you need any others??
Have the lads come back to build up internal walls and fireplaces?
what way are you going to screed off on top of the pre-cast floor?
Has the garage started yet, so you can finish that off and store the supplies in a safe and dry corner.
What are they going to ask you if you've decided on next?
Window sills is my next adventure, and then onto ensuite layouts for plumber before he comes back in 2 weeks time.

And don't mention the rain.
Terrible 2 weeks of wet weather, hardly a row of blocks go up each day. Yesterday 20th the guys were in full swing and 3 additional rows appeared on some walls.
ICF cutting out is fun.... Blocklayers ahve to clear a run each day on the ICF wall to tie the block wall into the concrete. I think i'll have to start chiselling away at the chimney spaces that need to come out. 2 sections of 5 ft by 9ft. that will take a while. My first major job on the house, roll up the sleeve and tuck in!

Tuesday, 5 June 2007

Ground floor External Walls up

Didn't get a photo of the finished floor, and now another week has passed and there are external walls up. ICF structure walls, for outside and inside central loadbearing wall.


Sunroom not done yet, blocks laid incorrectly to hold in the concrete being poured. Door from kitchen to sunroom wasn't cut out so that is to be cut now... special blades required for that. Not too bad a job given that i was off taking it easy in the Canaries for the week.
Next job is to get the concrete slab company in to measure up and they take 2weeks to deliver. meanwhile, garage walls are to commence this week and also internal block walls to be put in place.

Thursday, 17 May 2007

Next steps in foundations

Well finally after 2 weeks and 2 days, they are back on site again, and i have learnt what a "Whaker" is. Grade 804 stone (load after load) is being pressed into the foundations and a layer of dust over this. Radon barrier will be next.
Had some questions when I noticed the radon sump pipe was coming out the hole in the wall at the hotpress, which should be for the incoming heat and water! Bathroom - waste pipe also in the wrong place. And no exit pipe at the garage for the heating and water.

I am learning that you need to check every step along the way, and not be afraid to ask why is that there. Verify each step against your plans. Positions of all doors, facilities...
The guys have been very accommodating to putting them in the right place! A certain tact is required to say, "Hey, you've put them in the wrong place and i want it where it should be".

The hoover system goes in next and he is getting his schedule in a twist trying to accommodate me around the weather and his other work and very little notice. If it starts to delay things, i'll be skipping the "Nice to have" of an internal hoover system.

Staying calm and trying to reason with these guys that have this happening all the time is character building to say the least.

Here is the latest photo of proceedings.



Just realised this photo is a great shot to have a view of where all the pipes are running for future reference. Did do a floor plan of the run of pipes on my drawings aswell.

Later today, floors will be finished, all power floated etc.. another photo to follow.

Thursday, 3 May 2007

Foundation - next steps

May 2nd,
Foundation block work done for the house and garage.